Timeline: Difference between revisions
Jump to navigation
Jump to search
No edit summary |
m (→T-2 months) |
||
Line 31: | Line 31: | ||
==T-2 months== | ==T-2 months== | ||
* Speakers/Workshops confirmed and booked in | * [[Speakers_List | Speakers/Workshops]] confirmed and booked in | ||
==T-1 months== | ==T-1 months== |
Revision as of 11:27, 10 August 2013
Potential dates range: mid-July to mid-September 2014
T-12 months
- Site selected
- Date confirmed
- Food Vendor search begins
30/09/2013
- Ingenious Grant Applications close
T-6 months (but ideally by Nov 2013)
- Ticket sales open
- Promo materials made (fliers, limited t-shirts)
T-4 months
Deadline for orders:
- Baseload power
- Site lighting + scaff
- Network equipement/services
- Plant
- Telehandler
- Access equipment if reqd
- Site facilities ordered
- loos
- showers
- fencing
- containers
- tents
T-2 months
- Speakers/Workshops confirmed and booked in
T-1 months
- Badge production complete
- Badge software complete and in last testing stages
- Final timing schedule confirmed
T-2 weeks
- Program/flyers and any other printing works complete
Day -7
- Occupation of site
Day 1 - 3 (Fri-Sun)
- Event
Day 4-7
- Teardown