==T-12 months==
__NOTOC__
* Site selected
 
'''Update: Date for the event has been picked! (29-31 August)'''
 
==T-12 months (around August 2013)==
* [[Site_Search|Site selected]]
* Date confirmed
* Date confirmed
* Food Vendor search begins


==T-6 months (but ideally by Nov 2013)==
==T-6 months (around February 2014)==
* Ticket sales open
* Ticket sales open
* Promo materials made (fliers, limited t-shirts)
==T-4 months (around April 2014)==
Deadline for orders:
* Baseload power
* Site lighting + scaff
* Network equipement/services
* Plant
** Telehandler
** Access equipment if reqd
* Site facilities ordered
** loos
** showers
** fencing
** containers
** tents
==T-2 months (around June 2014) ==
* [[Speakers_List | Speakers/Workshops]] confirmed and booked in


==T-2 months==
==T-1 months (around July 2014) ==
* Power order finalised
* Badge production complete
* Badge software complete and in last testing stages
* Final timing schedule confirmed


==T-1 week==
==T-2 weeks (First weeks of August 2014) ==
* Program/flyers and any other printing works complete
 
==Day -7 (around 22nd of August) ==
* Occupation of site
* Occupation of site


==T-0==
==Day 1 - 3 (Fri-Sun)==
* 08:00 gates open
* Event
 
==Day 4-7==
* Teardown

Latest revision as of 08:21, 13 January 2014


Update: Date for the event has been picked! (29-31 August)

T-12 months (around August 2013)

T-6 months (around February 2014)

  • Ticket sales open
  • Promo materials made (fliers, limited t-shirts)

T-4 months (around April 2014)

Deadline for orders:

  • Baseload power
  • Site lighting + scaff
  • Network equipement/services
  • Plant
    • Telehandler
    • Access equipment if reqd
  • Site facilities ordered
    • loos
    • showers
    • fencing
    • containers
    • tents

T-2 months (around June 2014)

T-1 months (around July 2014)

  • Badge production complete
  • Badge software complete and in last testing stages
  • Final timing schedule confirmed

T-2 weeks (First weeks of August 2014)

  • Program/flyers and any other printing works complete

Day -7 (around 22nd of August)

  • Occupation of site

Day 1 - 3 (Fri-Sun)

  • Event

Day 4-7

  • Teardown