Timeline: Difference between revisions
Jump to navigation
Jump to search
m (You can't print until you know what's going in it...) |
No edit summary |
||
Line 28: | Line 28: | ||
==T+1 week== | ==T+1 week== | ||
* Organisers finally relax | * Organisers finally relax | ||
===Events to avoid=== | |||
* ICMP | |||
* Defcon? | |||
* Toorcamp? |
Revision as of 12:31, 8 May 2013
Potential date range: mid-July to mid-September 2014
T-12 months
- Site selected
- Date confirmed
T-6 months (but ideally by Nov 2013)
- Ticket sales open
T-2 months
- Power order finalised
T-3 weeks
- Final timing schedule confirmed
T-2 weeks
- Badge production complete
- Program/flyers and any other printing works complete
T-1 week
- Occupation of site
T-0
- 08:00 gates open
T+1 week
- Organisers finally relax
Events to avoid
- ICMP
- Defcon?
- Toorcamp?