Potential date range: mid-July to mid-September 2014
T-12 months
- Site selected
- Date confirmed
T-6 months (but ideally by Nov 2013)
- Ticket sales open
T-2 months
- Power order finalised
T-3 weeks
- Final timing schedule confirmed
T-2 weeks
- Badge production complete
- Program/flyers and any other printing works complete
T-1 week
- Occupation of site
T-0
- 08:00 gates open
T+1 week
- Organisers finally relax
Scheduling conflicts to avoid
- ICMP
- Defcon?
- Toorcamp?
- UK Bank holidays?