Timeline: Difference between revisions
Jump to navigation
Jump to search
Line 12: | Line 12: | ||
==T-4 months== | ==T-4 months== | ||
* | Deadline for orders: | ||
* Baseload power | |||
* Site lighting + scaff | |||
* Network bits ordered | * Network bits ordered | ||
* Site facilities ordered | * Site facilities ordered |
Revision as of 12:38, 8 May 2013
Potential date range: mid-July to mid-September 2014
T-12 months
- Site selected
- Date confirmed
T-6 months (but ideally by Nov 2013)
- Ticket sales open
- Promo materials made (fliers, limited t-shirts)
T-4 months
Deadline for orders:
- Baseload power
- Site lighting + scaff
- Network bits ordered
- Site facilities ordered
- loos
- showers
- fencing
- containers
- tents
T-3 weeks
- Final timing schedule confirmed
T-2 weeks
- Badge production complete
- Program/flyers and any other printing works complete
T-1 week
- Occupation of site
T-0
- 08:00 gates open
T+1 week
- Organisers finally relax
Scheduling conflicts to avoid
- ICMP
- Defcon?
- Toorcamp?
- UK Bank holidays?